Lutsenko S.A. Development of method for determining maximal ore output basing on the open-pit resource availability


Geoteh. meh. 2016, 130, 168-174

DEVELOPMENT OF METHOD FOR DETERMINING MAXIMAL ORE OUTPUT BASING ON THE OPEN-PIT RESOURCE AVAILABILITY
Lutsenko S.A.
State HEІ "KNU"

UDC 622.271:622.7.012

Abstract. Ore output is one of the main parameters of the open pit, which defines economic figures of any mineral opencast mining. The objective of the study is to improve methods for determining open-pit productivity with taking into account the required reserve volume available for extraction. The method for determining open-pit productivity has the following idea in its basis: mine productivity is to be determined basing not only on maximum intensity of mining operations (maximally possible arrangement of mining excavators), but also with taking into account interaction of width of operational area and length of active stripping front, which ensure a required volume of reserves available fo area width impacting on stripping zone length and volumes available for extraction. The results of completed studies may be used by design organizations and mining enterprises for evaluating any mine productivity.

Keywords: width of operational area, length of active stripping front, open-pit productivity, reserves available for extraction.

REFERENCES

 1. Trubetskoy, K.N., Krasnyanskiy, G.L., Hronin V.V. et al. (2009), Proektirovanie karerov [Designing quarries], Vysshaya shkola, Moscow, Russia.

2. Fomin, S.I., Ponomarev, А.I. and Shevelev, V.А. (2012), "Normalization of reserves available for extraction when generating mine operational zone", Journal of Tula State University: Soil Sciences, vol. 2, pp.176–183.

3. Shpanskiy, О.V., Ligotskiy, D.N. and Borisov, D.V. (2004), Proektirovanie proizvodstvennoy moshschnosti karerov [Designing of productive capacity of mine], Saint-Petersburg State University, Saint-Petersburg, Russia.

4. Arsentiev, А.I. (2002), Proizvoditelnost karerov [Mine productivity], Publishing House of Saint Petersburg Mining Institute, Saint-Petersburg, Russia.

5. Bliznyukov, V.G., Navitskiy, Yu. M. and Bliznyukova, О.Yu. (2015), "Possible adjustment of mining operations along with geometric analysis of mine field", Mining Journal, no.5, pp.50–51.

6. Kumachev, K.A. and Maymind, V.Ya. (1981), Proektirovanie zhelezorudnykh karerov [Designing of iron ore mines], Nedra, Moscow, USSR.

About the authors:

Lutsenko Sergei Aleksandrovich, Candidate of Technical Sciences (Ph.D.), Associate Professor, Associate Professor of Open-Cast Mining Department, State Higher Educational Institution ―Kryvoy Rog National University‖ (SHEI "KNU"), Kryvoy Rog, Ukraine, This email address is being protected from spambots. You need JavaScript enabled to view it. .