Kokoulin I.Ye., Yashchenko I.A., Mіroshnychenko V.V. Using the BOW-TIE method in analysis of aerological risks of coal mines
- Details
- Parent Category: Geo-Technical Mechanics, 2021
- Category: Geo-Technical Mechanics, 2021, Issue 156
Geoteh. meh. 2021, 156, 165-174
https://doi.org/10.15407/geotm2021.156.165
USING THE BOW-TIE METHOD IN ANALYSIS OF AEROLOGICAL RISKS OF COAL MINES
1Kokoulin I.Ye., 2Yashchenko I.A., 3Mіroshnychenko V.V.
1Institute of Geotechnical Mechanics named by N. Poliakov of NAS of Ukraine, 1Ministry of Power Engineering of Ukraine, 3LLC «DFEС»
UDC 622.8.012
Language: Ukrainian
Abstract. The coal industry in Ukraine remains one of the most dangerous industries. It is characterized by a wide range of accidents and emergencies, a high level of industrial injuries and occupational morbidity. The aim of improving production safety is not only to reduce the risk of injury and occupational morbidity (cases of high probability and insignificant), but also mine accidents, which occur relatively rarely, but are characterized by much more significant consequences. It is necessary to develop and use a risk analysis method that would take into account all aspects of the occurrence and course of a possible accident and would forecast in detail the elimination of its consequences. Ukraine still does not have an comprehensive legal and methodological support for assessing and managing emergency risks, and international standards on these issues, adapted to Ukrainian conditions, are not always brought to practical use. Risk assessment, especially aerological analysis, of a coal mine is a rather complicated process associated with the use of working methods in conditions of insufficient information, there are not enough specialists familiar with the methods of expert assessment, therefore, risk assessment methods well-known abroad are not used in the coal industry of Ukraine in full measure. One of these methods is the BOW-TIE diagram, which allows to simply and visually assess the advancing of a hazard from the place of the risk occurrence to the event that causes undesirable consequences, to determine the stages at which it is necessary to take emergency measures, the nature and reliability of such measures. The article presents the methods for constructing the BOW-TIE diagrams with different level of detail, routes of hazards advancing, establishment of risk control barriers, “brainstorming” during the analysis of aerological risks in order to reduce them to the acceptable level. Examples of using the BOW-TIE diagram are given. The use of foreign developments in domestic practice indicates the promising nature of this approach and the need to continue the work with the aim of wider introduction of this method at coal enterprises in Ukraine.
Keywords: coal mine, aerological risk, hazard, unwanted outcome, BOW-TIE method.
REFERENCES:
1. Federal Agency of the Russian Federation for Technical Regulation and Metrology (2010), GOST R 54145-2010 Menedzhment riskov. Rukovodstvo po primeneniyu organizatsionnykh mer bezopasnosti i otsenki riskov. Obshchaya metodologiya [GOST R 54145-2010 Risk management. Guidelines for the application of organizational security measures and risk assessment. General methodology], Moscow, RU.
2. Ministry of Economic Development of Ukraine (2015), DSTU IEC/ISO 31010:2013 Keruvannya ryzykom. Metody zahalʹnoho otsinyuvannya ryzyku [DSTU IEC/ISO 31010:2013 Risk management. Methods of general risk assessment], Kyiv, UA.
3. Ministry of Coal Industry of Ukraine (2010), NPAOP 10.0-1.01-10 Pravylabezpekyuvugilnykhshakhtakh [NLASL 10.0-1.01-10 Rules of safety in coal mines], Osnova, Kiev, UA.
4. Federal Agency of the Russian Federation for Technical Regulation and Metrology (2010), GOST R 54144-2010 Menedzhment riskov. Rukovodstvo po primeneniyu organizatsionnykh mer bezopasnosti i otsenki riskov.Identifikatsiya intsidentov[GOST R 54144-2010 Risk management. Guidelines for the application of organizational security measures and risk assessment. Identification of incidents], Moscow, RU.
5. Public Joint Stock Company "Gazprom Neft" (2016), M-16.07.01-02. versiya 01.Metodicheskiye ukazaniya po analízu i otsenke riskov PEB, OT i GZ s ispol'zovaniyem metoda BOW-TIE[M-16.07.01-02. version 01 Guidelines for the Analysis and Assessment of HSE, Occupational Health and Safety risks using the BOW-TIE method], Moscow, RU.
About the authors:
Kokoulin Ivan Yevhenovych, Candidate of Technical Sciences (Ph.D.), Senior Researcher, Senior Researcher in Department of Problems of Underground Mining at Great Depths, Institute of Geotechnical Mechanics named by N. Poljakov of National Academy of Sciences of Ukraine (IGTM NAS of Ukraine), Dnipro, Ukraine, This email address is being protected from spambots. You need JavaScript enabled to view it.
Yashchenko Ihor Oleksiovych, Candidate of Technscal Sciences (Ph.D.), Chіef of the Department of Labour Protection, Industrial Safety and Civil Defence, Ministry of Power Engineering of Ukraine, Kyiv, Ukraine.
Mіroshnychenko Vadym Volodymyrovych, Master of Science, Head of Ventilation and Degassing group Technical Develop-ment Department of Coal Production, Limited Liability Company «DFEС», Kyiv, Ukraine, This email address is being protected from spambots. You need JavaScript enabled to view it.