ESTIMATION METHOD OF PRODUCTION PRODUCTIVITY OF MINES IN MINING FACTOR
Sheyko A.V.
IGTM NAS of Ukraine
UDC [622.013.3:622.016]:65.012
Abstract. The method determination of project power by the mining factor of mines elaborative steep coal layers on deep horizons is improved in this work. A difference from the known methods is that loadings on lavas are determined taking into account a new conformity to the law of influencing of depth mining of coal layers and tectonic features of deposits on the outburst hazard of coal layers. The coefficient of simultaneity work of lavas is determined by a calculation way depending on the amount of working layers in the mine field and number of the simultaneously unsealed and worked floors. The conformities to the law of change of loadings on lavas and coefficient of simultaneous their work, set on the basis of generalization of experience mines for protracted period, are represented. Taking into account the represented method powers of mines on large depths and maximum depth of development of coal layers for the mines of the Central district of Donbassa, which on technscal-economical terms correspond to the depths of to 1500 м, are grounded. Progressive technological charts of dissection and preparation of layers are developed and ratified by Minugleprom of Ukraine.
Keywords: production capacity of mine, depth of development, loading on breakade face, gasdynamical activity of layer.
REFERENCES
1. Guryanov, V.V. (1994), "Main directions of scientific and technical progress in fuel industries of industry", Teploenergetyka., no. 11, pp. 11-16.
2. Ylyushenko, V.G., Leo, Ye.I. and Manczhula, S.A. (1992), "Rise stability of work of coal mines
(associations) of Donbassa in the conditions of market relations", Мoscow, RU.
3. Vylegzhanyn, V.N. (1996), "New introductions of the project providing of mines on all period of their development and sanatsyy", Announcer GMS of RAEN., pp. 159-165.
4. Starikov, А.V. (1999), "Development of theory and practice of management by mine works on coal mines", Мoscow, MSMU, MIAB, no. 3, pp. 58-60.
5. Puchkov, L.A., Krasyuk, N.N. and Reshetov, S.Ye. (2001), "Methodological principles and decisions on development of coal mines", Moscow, MSMU., RU.
6. Zaydenvarg, V.Ye. (1999), "Structural transformations in coal industry", Power policy., no. 3< pp. 25-31.
7. Malkin, A.S. (1996), "Appreciating of mine fund and increase of plenitude of the use of resources", Мoscow MSMU, RU.
8. Bunko, T.V. (2006), "Calculation vagueness of topology and aerodynamic parameters of the
ventilation systems at the calculation of economic feasibilities of mine on ventilation", Geotechnical
mechanics, no. 63, pp. 200-206.
9.Pushnoy, P.I.,Tkachenko N.M. and Anosov O.S. (1991) Progressivnye skhemy vskrytiyay i pogtovki krutykh plastov [Progressive opening schemes and preparation of steep seams], in Melnichuk, Yu.E.(e.d.), Tekhnika, Kiev, Ukraine.
About the authors:
Sheyko Anatoliy Vasilevich, chief technologist in Department of Underground Coal Mining,
M.S. Polyakov Institute of Geotechnical Mechanics under the National Academy of Science of Ukraine,
This email address is being protected from spambots. You need JavaScript enabled to view it.