ENSURED SUSTAINABILITY OF THE PREPARATORY ROADWAYS AT THE STAGES OF THEIR MINING AND EXPLOITATION

UDC 622.268.9: (430.1)

Authors:

Tsikra A.A., Ph. D. (Tech.),

Averkin D.I., M.S (Tech.) («Minova Ukraine» LTD),

Oprisko Y. S., M.S (Tech.),

Zaderiy V.V., M.S (Tech.) (IGTM NAN of Ukraine)

Abstract.

The paper presents findings on preparatory roadway state and peculiarities of ensuring sustainability at the initial stages of the roadways mining and exploitation in Donbass mines with complex geological conditions.

The research has stated that bolt-and-arch support twice reduces (to frame supports) a period of intensive roof-to-floor displacement. However, the problem still remains while developing the roadways in unstable water-saturated rocks.

The paper shows comparative characteristics of the roadways state in the process of their mining with and without backfilling of the fastened spaces. It is shown that mechanized backfilling by the fast-hardening mixtures not only increases bearing capacity of the surrounding rock massif due to the timely reaction of the arch support to the loads, but also allows blocking water and gas flowing into the roadway from the overlying rocks.

It is recommended to backfill fastened spaces in the roadway by TECHART packages of dry cement and mineral mixture produced by the Minowa Ukraine Ltd., usage of which was successfully tested in the mines of the “Makeevugol” state enterprise.

Keywords:

bolt-and-arch support, backfilling of the fastened space in the roadway.

References:

1. Baisarov, L.V., Iliasov, М.A. and Demchenko А.І. (2005), Geomekhanika y tehnologiya podderganiya povtorno ispolzuemyh vyrabotok [Geomechanics and maintain reusable technology developments], Lira, Dnepropetrovsk, Ukraine.

2. Bulat, A.F., Kurnosov, S.A. and Slashchyov, I.N. (2007), “Interaction of combined method of maintaining gas gathering workings with the coal bearing array”, Geotekhnicheskaya Mekhanika [Geo-Technical Mechanics], no. 68, pp. 24-36.

3. Iliashov, M.A., Kozhushonok, O.D. and Usachenko, B.M. (2009), “Combined security systems providing reuse workings of an excavation site”, Naukovi pratsi UkrNDMI of NAS of Ukraine [Scientific works of UkrNDMI of NAS of Ukraine], no. 5, Part 1, pp. 451-465.

4. Shrer, D. (1972), “Filling anhydrite clamping space excavation drifts”, Glückauf, no. 22, pp. 29-32.

5. Kammer, V. (1981), “Designing excavation drifts using new technology to fill a clamping space and the construction of allostreaming bands”, Glückauf, no. 17, pp. 9-11.

6. Tuchin, A.S. and Skalicki, Z. (2001), “Mineral-cement materials of the company "Fosroc – Poland" in Ukraine”, Coal of Ukraine, no. 9, pp. 51-54.

7. Bulat, A.F., Usachenko, B.M. and Levchenko, L.V. (2006), “By the choice of mixes for mining technologies”, Geotekhnicheskaya Mekhanika [Geo-Technical Mechanics], no. 61, pp. 27-41.

8. Baisarov, L.V., Torres, V.A., Iliashov, M.A. [ect.] (2002), “Optimization formulations for shtrekovih bands”, Proceedings of the Donetsk Institute of Mining, no. 1, pp. 16-18.

About the authors:

Tsikra Alexander Anatolyevich, Candidate of Technical Sciences (Ph.D), Technical director of «Minova Ukraine» LTD, Donetsk, Ukraine, Ця електронна адреса захищена від спам-ботів. вам потрібно увімкнути JavaScript, щоб побачити її.

Averkin Dmitry Ivanovich, Master of Science, Deputy Director of «Minova Ukraine» LTD, Donetsk, Ukraine, Ця електронна адреса захищена від спам-ботів. вам потрібно увімкнути JavaScript, щоб побачити її.

Opryshko Yury Sergeevich, chief technologist IGTM, Dnepropetrovsk, Ukraine, Ця електронна адреса захищена від спам-ботів. вам потрібно увімкнути JavaScript, щоб побачити її.

Zaderiy Vladimir Vasilyevich, Engineer in IGTM, Dnepropetrovsk, Ukraine, Ця електронна адреса захищена від спам-ботів. вам потрібно увімкнути JavaScript, щоб побачити її.